Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
NE ASR Enhanced Arroyo Phase 1
McCombs Street - 1 mile north of US-54 west of Painted Dunes Desert Golf Course, El Paso, TX 79934, El Paso, TX, 79934
Final Inspection85%
๐Project Metrics
TDLR #TABS2024011776$6.3M
Project Value
1,001,880
Square Feet
$6/sqft
Cost/SqFt
4 months
Duration
Registered:Feb 16, 2024
Start:Feb 22, 2024
Target:Jun 22, 2024
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
The project infrastructure is planned to construct an enhanced arroyo starting from the right-of-way at McCombs going west for appx 3500 LF. The project includes landscaing amenities with a hike and bike trails.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 16, 2024
Construction Start
February 22, 2024
Expected Completion
June 22, 2024