๐Project Registered๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Wedgwood Middle School Addition & Renovation
3909 Wilkie Way,, Fort Worth, TX 76133, Fort Worth, TX, 76133
Pre-Construction15%
๐Project Metrics
TDLR #TABS2024013634$44.0M
Project Value
170,000
Square Feet
$259/sqft
Cost/SqFt
2y 3mo
Duration
Registered:Mar 12, 2024
Start:Apr 15, 2024
Target:Jul 1, 2026
Remaining:194 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Renovating the entire existing school as well as two connected additions to the facility.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 12, 2024
Construction Start
April 15, 2024
Expected Completion
July 1, 2026
๐Related Projects
Property Owner
๐ค
Fort Worth ISD
Contact: Nate Moser
4 projects ยท $160.4M