๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

BP PULSE EV CHARGING STATIONS 426 SWEETWATER, TX

100 HOPKINS RD, Sweetwater, TX 79556, Sweetwater, TX, 79556
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024014314
$175K
Project Value
500
Square Feet
$350/sqft
Cost/SqFt
1 months
Duration
Registered:Mar 20, 2024
Start:Aug 6, 2024
Target:Sep 17, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

INSTALL 6 LEVEL 3 ELECTRIC VEHICLE CHARGING STATIONS IN EXISTING PARKING LOT

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 20, 2024
Construction Start
August 6, 2024
Expected Completion
September 17, 2024