Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024017415
$1.5M
Project Value
120,500
Square Feet
$12/sqft
Cost/SqFt
5 months
Duration
Registered:May 1, 2024
Start:May 20, 2024
Target:Oct 31, 2024
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Restoration of Historic Standpipe, new concrete walking trails, new parking lot, new restroom facility, new shade structure and playground area.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 1, 2024
Construction Start
May 20, 2024
Expected Completion
October 31, 2024