๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
TWC ADMINISTRATION ADA
7210 82ND STREET, Lubbock, TX 79424, Lubbock, TX, 79424
Completed100%
๐Project Metrics
TDLR #TABS2024018744$210K
Project Value
700
Square Feet
$300/sqft
Cost/SqFt
6 months
Duration
Registered:May 16, 2024
Start:Jun 20, 2024
Target:Dec 3, 2024
๐
Project Closed
Project has been completed and closed
๐Scope of Work
ADA access from the existing parking lot to the NextGen south entry and ramp access inside the NextGen facility from the terrace to the worship area.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 16, 2024
Construction Start
June 20, 2024
Expected Completion
December 3, 2024