๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
City of Breckenridge 2022 TXCDBG-DRP Project
Intersection of N. Rose Street and W. Elm Street, Breckenridge, TX 80424, Breckenridge, TX, 80424
Completed100%
๐Project Metrics
TDLR #TABS2024019513$434K
Project Value
9,972
Square Feet
$44/sqft
Cost/SqFt
9 months
Duration
Registered:May 29, 2024
Start:Jul 15, 2024
Target:Apr 1, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Demolition and replacement of approx 1,108 sq yards of sidewalk, asphalt, and concrete driveways, asl well as approx 565 LF of curb and gutter around the intersection of N. Rose Street and W. Elm Street
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 29, 2024
Construction Start
July 15, 2024
Expected Completion
April 1, 2025
๐Related Projects
Property Owner
๐ค
City of Breckenridge
Contact: Cynthia Northrop
105 North Rose Avenue, Breckenridge, Texas 80424
Design Firm
๐๏ธ
Enprotec/Hibbs & Todd Inc.
3 projects ยท $1.1M