๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

LISD Dr. Leonides Cigarroa High School Phase 2

2600 Zacatecas St., Laredo, TX 78046, Laredo, TX, 78046
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2024024851
$33.0M
Project Value
5,782,075
Square Feet
$6/sqft
Cost/SqFt
2y 3mo
Duration
Registered:Aug 6, 2024
Start:Oct 1, 2024
Target:Dec 10, 2026
Remaining:354 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Demolition of existing classrooms to allow for a new 57,820.75 SF two story building for CTE Classrooms and Shops

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 6, 2024
Construction Start
October 1, 2024
Expected Completion
December 10, 2026