๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Tyler Pedestrian Access
City of Tyler - Multiple Locations, Tyler, TX 75701, Tyler, TX, 75701
Construction50%
๐Project Metrics
TDLR #TABS2024026398$500K
Project Value
24,000
Square Feet
$21/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Aug 27, 2024
Start:Nov 1, 2024
Target:Jul 22, 2026
Remaining:212 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Replacement and construction of new pedestrian sidewalks, crosswalks, ramps and bus stops at multiple locations
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 27, 2024
Construction Start
November 1, 2024
Expected Completion
July 22, 2026
๐Related Projects
๐คSame Owner
$9.5M total๐๏ธSame Design Firm
$3.4M totalProperty Owner
๐ค
City of Tyler
Contact: Davis Dickson
4 projects ยท $9.5M
423 W Ferguson St, Tyler, Texas 75702