๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Western Hills Elementary
600 Arapahoe Dr, Temple, TX 76504, Temple, TX, 76504
Construction50%
๐Project Metrics
TDLR #TABS2025000336$2.5M
Project Value
3,500
Square Feet
$714/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Sep 6, 2024
Start:Dec 18, 2024
Target:Dec 31, 2025
Remaining:9 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Addition of two classrooms and minor renovations
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 6, 2024
Construction Start
December 18, 2024
Expected Completion
December 31, 2025