๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Japhet ES - Expansive Soil Repairs Phase 2

314 Astor St., San Antonio, TX 78210, San Antonio, TX, 78210
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025000389
$337K
Project Value
8,276
Square Feet
$41/sqft
Cost/SqFt
2 months
Duration
Registered:Sep 6, 2024
Start:Dec 1, 2024
Target:Feb 1, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Expansive soil repairs, drainage improvements, removing and replacing existing asphalt pavement and sidewalk/flat work.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 6, 2024
Construction Start
December 1, 2024
Expected Completion
February 1, 2025

Quick Actions

TDLR ID: TABS2025000389

Property Owner

Design Firm

๐Ÿ›๏ธ
MTR Engineers
4 projects ยท $1.3M
12770 Cimarron Path Suite 100, San Antonio, Texas 78249

Registered Accessibility Specialist

๐Ÿ“‹
SHAWN,KAARLSEN
RAS #343
13438 BANDERA RD STE 202, HELOTES, TX 78023