Dallas Water Utilities WTP Laboratory Renovation

405 Long Creek Road, Sunnyvale, TX 75182, Sunnyvale, TX, 75182
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025000831
$10.2M
Project Value
7,095
Square Feet
$1.44K/sqft
Cost/SqFt
2y 3mo
Duration
Registered:Sep 12, 2024
Start:Nov 1, 2024
Target:Jan 11, 2027
Remaining:385 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Renovation and expansion of existing 5,500 sqft Water Testing Lab at Eastside Water Treatment Plant for Dallas Water Utility. Scope Captures additional second floor space and first floor carport to expand water testing lab to 7,100 sqft.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 12, 2024
Construction Start
November 1, 2024
Expected Completion
January 11, 2027

Quick Actions

TDLR ID: TABS2025000831

Property Owner

Design Firm

๐Ÿ›๏ธ
GSR Andrade Architects
4 projects ยท $11.9M
2001 North Lamar Street Suite #400, Dallas, Texas 75202

Registered Accessibility Specialist

๐Ÿ“‹
JEFFERY L,KELLEY
RAS #55
780 N WATTERS RD STE 150, ALLEN, TX 75013