๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
East Central ISD - South Elementary School
17150 Sage Common, Elmendorf, TX 78223, Elmendorf, TX, 78223
Construction50%
๐Project Metrics
TDLR #TABS2025001171$45.0M
Project Value
100,000
Square Feet
$450/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Sep 17, 2024
Start:Nov 4, 2024
Target:May 31, 2026
Remaining:160 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
THE EAST CENTRAL ISD SOUTH ELEMENTARY SCHOOL IS A NEW CONSTRUCTION, PARTIAL TWO-STORY EDUCATIONAL BUILDING COMPOSED OF GENERAL ACADEMICS, SPECIAL EDUCATION, LIBRARY, GYMNASIUM, DINING/KITCHEN, ADMINISTRATION AND SUPPORT SPACES SERVING GRADES PRE-KIND
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 17, 2024
Construction Start
November 4, 2024
Expected Completion
May 31, 2026
๐Related Projects
๐คSame Owner
$241.4M totalProperty Owner
๐ค
East Central Independent School District
Contact: John Thomas
4 projects ยท $241.4M
6634 Sulphur Springs Rd., San Antonio, Texas 78263
Design Firm
๐๏ธ
LPA, Inc.
4 projects ยท $62.8M
1811 S Alamo St UNIT 100, San Antonio, Texas 78204