๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

L.D. Bell High School Replacement

1601 Brown Trail, Hurst, TX 76054, Hurst, TX, 76054
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025002532
$292.1M
Project Value
546,403
Square Feet
$535/sqft
Cost/SqFt
4y 7mo
Duration
Registered:Oct 4, 2024
Start:Feb 3, 2025
Target:Jul 31, 2029
Remaining:1320 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

This project is the demolition of the existing LD Bell High School and new construction of a new LD Bell High School. The new high school is on the same site and will be built in two phases. Phase 2 will be the demolition of the existing high school.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 4, 2024
Construction Start
February 3, 2025
Expected Completion
July 31, 2029

Quick Actions

TDLR ID: TABS2025002532

Design Firm

๐Ÿ›๏ธ
Corgan
4 projects ยท $25.8M
401 N Houston Street, Dallas, Texas 75202

Registered Accessibility Specialist

๐Ÿ“‹
RONALD L,DAVIS
RAS #83
3001 MOTLEY DR STE J, MESQUITE, TX 75150