๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Ingram HS Science Classroom and Lab Wing Addition
510 TX-39, Ingram, TX 78025, Ingram, TX, 78025
Construction50%
๐Project Metrics
TDLR #TABS2025005372$3.8M
Project Value
9,841
Square Feet
$389/sqft
Cost/SqFt
9 months
Duration
Registered:Nov 12, 2024
Start:Nov 25, 2024
Target:Aug 29, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
The addition of 2 classrooms, 2 science labs, and an art room, along with restrooms and support spaces. The new addition will be constructed of concrete slab on grade, pre-engineered metal building, metal roof and EIFS. Utilities will be extended.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 12, 2024
Construction Start
November 25, 2024
Expected Completion
August 29, 2025
๐Related Projects
๐คSame Owner
$7.5M totalProperty Owner
๐ค
Ingram Independent School District
Contact: Don May
4 projects ยท $7.5M
644 Hwy 39, Ingram, Texas 78025
Design Firm
๐๏ธ
Alvarado Architects & Associates, Inc.
4 projects ยท $24.2M
307 South Main Street, Donna, Texas 78537