๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
North Forest Subdivision Drainage Improvements 2018
East of Ella Blvd. and North of W. Richey Road, Houston, TX 77090, Houston, TX, 77090
Construction50%
๐Project Metrics
TDLR #TABS2025006548$170K
Project Value
1,206
Square Feet
$141/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Nov 27, 2024
Start:Jan 13, 2025
Target:Jul 7, 2026
Remaining:200 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Proposed sidewalk, crosswalks, pedestrian ramps, and concrete path. (Sidewalk area= 1206 SF).
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 27, 2024
Construction Start
January 13, 2025
Expected Completion
July 7, 2026
๐Related Projects
๐คSame Owner
$17.1M totalProperty Owner
๐ค
Harris County
Contact: Umar Latiff
4 projects ยท $17.1M
1111 Fannin St. 11th Floor, Houston, Texas 77002
Design Firm
๐๏ธ
PGAL, Inc.
4 projects ยท $192.0M
3131 Briarpark Drive, Suite 200, Houston, Texas 77042