๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
GCCM Holdings, LLC Cement Terminal Addition
1800 E. Navigation Blvd., Corpus Christi, TX, 78402
Construction50%
๐Project Metrics
TDLR #TABS2025007555$750K
Project Value
3,200
Square Feet
$234/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Dec 12, 2024
Start:Feb 21, 2025
Target:Jun 26, 2026
Remaining:198 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
single story, fully conditioned, 3,200 SF building with mechanical room, offices, and warehouse/maintenance facility
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 12, 2024
Review Complete
December 12, 2024
Construction Start
February 21, 2025
Expected Completion
June 26, 2026