๐Ÿ“‹Project Registered๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2022 Bond Year 2 Contract 11

Multiple Locations, Fort Worth, TX, 76110
Pre-Construction15%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025007711
$11.5M
Project Value
417,000
Square Feet
$28/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Dec 16, 2024
Start:Mar 1, 2025
Target:May 1, 2026
Remaining:142 days
๐Ÿ“‹

Project Registered

Project has been registered with TDLR and is in pre-construction phase

๐Ÿ“‹Scope of Work

Paving improvements include 19,302 SY of 6'' Concrete Pavement, 15,710 SY of 3'' Asphalt Pavement, 44,133 SF of 4'' Concrete Sidewalk, 23 varied Barrier Free Ramps, and 57,333 SF of Concrete Driveway, as well as Water and San Sewer improvements.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 16, 2024
Construction Start
March 1, 2025
Expected Completion
May 1, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025007711

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
RONALD L,DAVIS
RAS #83
3001 MOTLEY DR STE J, MESQUITE, TX 75150