๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
US Hwy 83 TLP Phase 1
TBD, Laredo, TX, 78041
Construction50%
๐Project Metrics
TDLR #TABS2025007896$15.0M
Project Value
239,689
Square Feet
$63/sqft
Cost/SqFt
9 months
Duration
Registered:Dec 17, 2024
Start:May 26, 2025
Target:Feb 27, 2026
Remaining:79 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
237,005 sq ft of Tilt-wall industrial shell building with approx 2,684 of spec tenant space
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 17, 2024
Review Complete
December 17, 2024
Construction Start
May 26, 2025
Expected Completion
February 27, 2026
๐Related Projects
๐คBy Owner
$60.0M totalProperty Owner
๐ค
Stewart Development
Contact: Wilson Santos
4 projects ยท $60.0M
23000 NW Lake Drive, Houston, Texas 77095
Design Firm
๐๏ธ
Method Architecture
6 projects ยท $5.3M
200 E Grayson Street, Suite 122, San Antonio, Texas 78215