๐Review Complete๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
Melton Electric Phase 2
2315 Karbach, Houston, TX, 77092
Construction50%
๐Project Metrics
TDLR #TABS2025007976$4.4M
Project Value
26,988
Square Feet
$163/sqft
Cost/SqFt
1 year
Duration
Registered:Dec 18, 2024
Start:Feb 24, 2025
Target:Feb 23, 2026
Remaining:75 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Renovation of existing one-story storage warehouse, fab shop, and office.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 18, 2024
Review Complete
December 18, 2024
Construction Start
February 24, 2025
Expected Completion
February 23, 2026
๐Related Projects
Property Owner
Design Firm
๐๏ธ
Kirksey Architecture
6 projects ยท $256.5M
6909 Portwest Drive, Houston, Texas 77024