Segment 11A
24106 Cinco Ranch Blvd, Katy, TX, 77494
Completed100%
๐Project Metrics
TDLR #TABS2025008145$7.6M
Project Value
28,650
Square Feet
$264/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Dec 19, 2024
Start:Oct 9, 2023
Target:Jan 31, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Proposed 36" waterline along Willow Fork of Buffalo Bayou and Ditch VA3 from SH99 to Cinco MUD No.1 Pan construction includes the removal and replacement of approximately 28,650sf of concrete hike & bike trail
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 19, 2024
Project Closed
December 19, 2024
Construction Start
October 9, 2023
Expected Completion
January 31, 2025
Property Owner
๐ค
North Fort Bend Water Authority
Contact: Peter Houghton (President)
c/o Allen Boone Humphries Robinson 3200 Southwest Freeway Suite 2500, Houston, Texas 77027