โ
Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Phase 3 Boardwalk District Trails
7322 Southwest Fwy, Suite 1040, Houston, TX, 77040
Final Inspection85%
๐Project Metrics
TDLR #TABS2025008523$2.0M
Project Value
17,100
Square Feet
$117/sqft
Cost/SqFt
7 months
Duration
Registered:Dec 27, 2024
Start:Apr 1, 2025
Target:Oct 31, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Scope of Work of the Contract includes the construction of a 12-foot-wide trail system around a detention pond, and a new trail extension connecting the existing trails to Kingsland Boulevard.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 27, 2024
Inspection Complete
December 27, 2024
Construction Start
April 1, 2025
Expected Completion
October 31, 2025
๐Related Projects
๐๏ธBy Design Firm
$2.2M totalProperty Owner
๐ค
Katy Management District No. 1
Contact: David Kasper
901 Avenue C, Katy, Texas 77493
Design Firm
๐๏ธ
ARKK Engineers
2 projects ยท $2.2M
7322 Southwest Freeway, Suite 1040, Houston, Texas 77074