๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

SH 6 (CSJ: 0049-12-110, etc.)

From: SH 21 To: SH 40, Bryan, TX, 77803
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025008526
$11.6M
Project Value
807,500
Square Feet
$14/sqft
Cost/SqFt
5y 3mo
Duration
Registered:Dec 27, 2024
Start:Aug 1, 2025
Target:Oct 1, 2030
Remaining:1756 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Widen freeway facility from 4 to 6 lanes, improve frontage roads, add local access and bicycle/ped facilities.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 27, 2024
Review Complete
December 27, 2024
Construction Start
August 1, 2025
Expected Completion
October 1, 2030

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025008526

Design Firm

๐Ÿ›๏ธ
Jacobs Solutions Inc.
2705 Bee Cave Road, Suite 300, Austin, Texas 78746

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201