๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
The Goddard School Round Rock TX
4850 Lunata Way, Round Rock, TX, 78626
๐Project Overview
$4.0M
Est. Cost
12,900
Square Feet
6 months
Duration
Complete
Status
๐Scope of Work
NEW GODDARD SCHOOLS EARLY CHILDHOOD EDUCATION FACILITY. THE SCHOOL WILL BE A GROUND-UP, SINGLE-STORY, WOOD FRAMED BUILDING WITH APPROXIMATELY 12,900 SQUARE FEET CONTAINING 12 CLASSROOMS.
๐ Project Timeline
Registered
December 30, 2024
Review Complete
December 30, 2024
Construction Start
April 1, 2025
Expected Completion
October 1, 2025
๐บ๏ธLocation
๐Related Projects
Property Owner
Design Firm
Registered Specialist
๐
RICHARD TODD,LOZANO
RAS #93
6101 WOODVIEW AVE, AUSTIN, TX 78757
(512) 374-1696