๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

EPIA Dust Off By Pass D B

Bypass between Constitution Ave and Iron Dust Dr, El Paso, TX, 79925
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025009054
$4.2M
Project Value
104,805
Square Feet
$40/sqft
Cost/SqFt
9 months
Duration
Registered:Jan 8, 2025
Start:Apr 1, 2025
Target:Jan 1, 2026
Remaining:11 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Scope includes an approximate 1,500-foot-long road (104,805 SF) bypass between Constitution Avenue and Iron Dust Drive, ADA compliant sidewalks, curb and gutter, illumination, and landscaped median.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 8, 2025
Review Complete
January 8, 2025
Construction Start
April 1, 2025
Expected Completion
January 1, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|31.83899, -106.33736

Quick Actions

TDLR ID: TABS2025009054

Property Owner

Design Firm

๐Ÿ›๏ธ
Parkhill
4 projects ยท $25.2M
501 West San Antonio, El Paso, Texas 79901

Registered Accessibility Specialist

๐Ÿ“‹
ECKHARD K,FENNIG
RAS #476