📝Review Complete🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
Moonlight Musical Amphitheater Erosion Control
413 East Broadway, Lubbock, TX, 79403
Construction50%
📊Project Metrics
TDLR #TABS2025010111$350K
Project Value
20,000
Square Feet
$18/sqft
Cost/SqFt
8 months
Duration
Registered:Jan 22, 2025
Start:Feb 24, 2025
Target:Nov 1, 2025
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Sitework and light concrete to aide in drainage and erosion control for the Moonlight Musical Amphitheater.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
January 22, 2025
Review Complete
January 22, 2025
Construction Start
February 24, 2025
Expected Completion
November 1, 2025