📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Leander ISD Early Childhood Center
southeast corner of halsey dr and san gabriel park, Leander, TX, 78641
📊Project Overview
$48.2M
Est. Cost
102,000
Square Feet
1y 4mo
Duration
243
Days Left
📋Scope of Work
New construction of a 1-story pre K elementary school on an undeveloped site. The school will have parking, bus drop off, classrooms and outdoor areas.
📅Project Timeline
Registered
January 24, 2025
Review Complete
January 24, 2025
Construction Start
April 1, 2025
Expected Completion
July 31, 2026
🗺️Location
Property Owner
👤
Leander Indepent School District
Contact: Lori Black
301b South West Dr, Leander, Texas 78641
(512) 925-7419
Registered Specialist
📋
KATHY ANN,RILEY
RAS #254
1408 NORTHRIDGE DR, AUSTIN, TX 78723
(512) 762-6349