Brock ISD | New Multipurpose Student Center
400 Eagle Spirit Lane, Brock, TX, 76087
Construction50%
๐Project Metrics
TDLR #TABS2025010425$16.6M
Project Value
73,924
Square Feet
$225/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Jan 27, 2025
Start:Mar 17, 2025
Target:May 11, 2026
Remaining:152 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Multipurpose Student Center
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 27, 2025
Review Complete
January 27, 2025
Construction Start
March 17, 2025
Expected Completion
May 11, 2026
๐Related Projects
Property Owner
Design Firm
๐๏ธ
Huckabee
6 projects ยท $20.6M
801 Cherry Street Ste. 500, Fort Worth, Texas 76102