๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
2025 Wright Elementary Playground Improvement Project
1702 S Grinnell St., Perryton, TX, 79070
Construction50%
๐Project Metrics
TDLR #TABS2025010583$360K
Project Value
51,050
Square Feet
$7/sqft
Cost/SqFt
3 months
Duration
Registered:Jan 29, 2025
Start:May 26, 2025
Target:Aug 22, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Replace pavement approx. 26,000sf, Install grass field 12,800sf, new sidewalks 6,250sf, maintenance and installation of new play equipment 6,000sf.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 29, 2025
Review Complete
January 29, 2025
Construction Start
May 26, 2025
Expected Completion
August 22, 2025
๐Related Projects
๐คBy Owner
$4.0M totalProperty Owner
๐ค
Perryton ISD Trustees
Contact: Greg Brown, Superintendent
2 projects ยท $4.0M
821 SW 17th Ave, Perryton, Texas 79070