๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Celina Government Center

100 North Colorado Street, Celina, TX, 75009
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025011490
$59.1M
Project Value
87,300
Square Feet
$676/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Feb 10, 2025
Start:May 1, 2025
Target:Aug 24, 2026
Remaining:257 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

A new government center building 4 stories tall with a basement to house a public library and government offices as well as public meeting & event spaces, along with an occupied roof deck.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 10, 2025
Review Complete
February 10, 2025
Construction Start
May 1, 2025
Expected Completion
August 24, 2026

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025011490

Design Firm

๐Ÿ›๏ธ
HED
3 projects ยท $134.4M
15301 Spectrum Drive Suite 450, Addison, Texas 75001

Registered Accessibility Specialist

๐Ÿ“‹
KIMBERLY J,GOSS
RAS #51
12720 HILLCREST ROAD STE 1040, DALLAS, TX 75230