📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
ASU Plant Office Building-Brownsville
7245 Industrial Circle, Brownsville, TX, 78526
Construction50%
📊Project Metrics
TDLR #TABS2025011717$200K
Project Value
1,450
Square Feet
$138/sqft
Cost/SqFt
1 year
Duration
Registered:Feb 12, 2025
Start:Feb 12, 2025
Target:Feb 12, 2026
Remaining:64 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Office Building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 12, 2025
Review Complete
February 12, 2025
Construction Start
February 12, 2025
Expected Completion
February 12, 2026