📝Review Complete🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
RECONSTRUCTION OF WALTON DR
WALTON DR MULTIPLE LOCATIONS, Corinth, TX, 76210
Construction50%
📊Project Metrics
TDLR #TABS2025012213$4.9M
Project Value
136,000
Square Feet
$36/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Feb 18, 2025
Start:Apr 1, 2025
Target:May 1, 2026
Remaining:142 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
ROADWAY, RETAINING WALL AND STORM SYSTEM
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 18, 2025
Review Complete
February 18, 2025
Construction Start
April 1, 2025
Expected Completion
May 1, 2026