โ
Inspection Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Taco Bell Restaurant
408 W Griffin Pkwy, Mission, TX, 78572
Final Inspection85%
๐Project Metrics
TDLR #TABS2025012510$1.1M
Project Value
2,494
Square Feet
$441/sqft
Cost/SqFt
4 months
Duration
Registered:Feb 21, 2025
Start:Jun 16, 2025
Target:Oct 1, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Construction of a new Taco Bell Restaurant with related site work.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 21, 2025
Inspection Complete
February 21, 2025
Construction Start
June 16, 2025
Expected Completion
October 1, 2025