๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Greenwood High School CTE and Additionals & Renovations Phase 1
2700 FM 1379, Midland, TX, 79706
Construction50%
๐Project Metrics
TDLR #TABS2025012943$15.8M
Project Value
34,500
Square Feet
$458/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Feb 27, 2025
Start:Apr 2, 2025
Target:Oct 4, 2026
Remaining:298 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Project consists of a 30,000 s.f addition for CTE spaces and interior renovation of approximately 4,500 s.f. for Lifeskills area.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 27, 2025
Review Complete
February 27, 2025
Construction Start
April 2, 2025
Expected Completion
October 4, 2026
๐Related Projects
Property Owner
๐ค
Greenwood ISD
Contact: Ariel Elliott
3 projects ยท $109.0M
2700 FM 1379, Midland, Texas 79706