📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
HSISD Field House
701 Russell, Hughes Springs, TX, 75656
Construction50%
📊Project Metrics
TDLR #TABS2025013382$5.0M
Project Value
12,300
Square Feet
$407/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Mar 5, 2025
Start:Apr 7, 2025
Target:Jul 31, 2026
Remaining:233 days
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Construct new single story student athletic facility of approximately 7,625 sf, and addition/alteration to an existing single story student locker room facility of approximately 4,676 sf, as well as site improvements.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
March 5, 2025
Review Complete
March 5, 2025
Construction Start
April 7, 2025
Expected Completion
July 31, 2026
Property Owner
👤
Hughes Springs Independent School District
Contact: Sarah Dildine
871 Taylor, Hughes Springs, Texas 75656