๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
ExxonMobil Beaumont Machine Weld Shop
2700 Sycamore St., Beaumont, TX, 77701
Completed100%
๐Project Metrics
TDLR #TABS2025013427$50.0M
Project Value
76,000
Square Feet
$658/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Mar 5, 2025
Start:May 1, 2023
Target:Mar 31, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
76,000 square-foot industrial building at ExxonMobil's Beaumont refinery, including a machine shop, weld shop, two story office unit, and various ancillary support spaces.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 5, 2025
Project Closed
March 5, 2025
Construction Start
May 1, 2023
Expected Completion
March 31, 2025
๐Related Projects
๐คBy Owner
$50.4M total๐๏ธBy Design Firm
$3.2M totalAlterations to ExxonMobil Facilities, Main Campus (Nature 4), Level 2
Springยท$253K
Alterations to ExxonMobil Facilities, Main Campus (Nature 4), Level 3
Springยท$355K
Alterations to ExxonMobil Facilities, Main Campus (Nature 4), Level 6
Springยท$323K
Alterations to ExxonMobil Facilities, Main Campus (Nature 4), Level 4
Springยท$414K
Property Owner
๐ค
ExxonMobil
Contact: Grady Gammons
2 projects ยท $50.4M
22777 Springwoods Village Parkway, Spring, Texas 77389
Design Firm
๐๏ธ
Schwarz-Hanson Architects
6 projects ยท $3.2M
2627 Tillar Street, Suite 131, Fort Worth, Texas 76107