๐Review Complete๐ง Additions to Existing Building๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Additions
2400 Hwy 12, Vidor, TX, 77662
Construction50%
๐Project Metrics
TDLR #TABS2025014204$6.4M
Project Value
12,442
Square Feet
$518/sqft
Cost/SqFt
11 months
Duration
Registered:Mar 14, 2025
Start:Apr 1, 2025
Target:Feb 28, 2026
Remaining:80 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New classroom addition
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 14, 2025
Review Complete
March 14, 2025
Construction Start
April 1, 2025
Expected Completion
February 28, 2026
๐Related Projects
Property Owner
๐ค
Vidor ISD
Contact: Dr. Travis Maines
5 projects ยท $52.2M
1255 N Main, Vidor, Texas 77662