📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.
The Crossing at Carmel Creek - East Tract
402 Diamond Hitch Drive, Hutto, TX, 78634
📊Project Overview
$1.8M
Est. Cost
141,000
Square Feet
10 months
Duration
121
Days Left
📋Scope of Work
Landscape project contains over 125,000 SF open space, miles of trails, 7,500 SF dog park, picnic tables/ seating areas, over 9,000 SF of planting areas and irrigation
📅Project Timeline
Registered
March 25, 2025
Review Complete
March 25, 2025
Construction Start
June 1, 2025
Expected Completion
March 31, 2026
🗺️Location
Property Owner
Design Firm
Registered Specialist
📋
STEPHEN A,MEYER
RAS #1078
323 W AGARITA AVE, SAN ANTONIO, TX 78212
(210) 250-1651