๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
KISD Wunderlich Intermediate School Renovations
11800 Misty Valley Drive, Houston, TX, 77066
Construction50%
๐Project Metrics
TDLR #TABS2025015235$37.0M
Project Value
165,400
Square Feet
$224/sqft
Cost/SqFt
1y 2mo
Duration
Registered:Mar 27, 2025
Start:Jun 2, 2025
Target:Jul 31, 2026
Remaining:233 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Major renovations to Wunderlich Intermediate School, including interior and reconfiguration, life safety upgrades, and building additions.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 27, 2025
Review Complete
March 27, 2025
Construction Start
June 2, 2025
Expected Completion
July 31, 2026
๐Related Projects
๐คBy Owner
$90.3M total๐๏ธBy Design Firm
$37.5M totalProperty Owner
๐ค
Klein Independent School District
Contact: Danny Phillips
4 projects ยท $90.3M
7200 Spring Cypress Road, Klein, Texas 77379
Design Firm
๐๏ธ
BRW Architects, Inc.
2 projects ยท $37.5M
4501 Magnolia Cove Drive Suite 250, Houston, Texas 77345