📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

5MW Temple Data Center

2313 Eberhardt Road, Temple, TX, 76504
Construction50%

📊Project Metrics

TDLR #TABS2025015318
$31.0M
Project Value
61,554
Square Feet
$504/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Mar 28, 2025
Start:Jul 14, 2025
Target:Oct 16, 2026
Remaining:310 days
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

A new 61,5191 MW data center including construction of new exterior and interior partitions, ceilings, finishes, mechanical, electrical, plumbing, and fire protection. Also, includes site work, data hall #1, admin. area, and tilt-wall panels.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
March 28, 2025
Review Complete
March 28, 2025
Construction Start
July 14, 2025
Expected Completion
October 16, 2026

🗺️Project Location

Loading map...

Quick Actions

TDLR ID: TABS2025015318

Property Owner

👤
Oppidan
Contact: Greg LaVere
400 Water Street, Suite 200, Excelsior, Minnesota 55331

Design Firm

🏛️
Salas O'Brien
10202 5th Ave NE, Suite 300, Seattle, Washington 98125

Registered Accessibility Specialist

📋
JUSTIN K,WALTON
RAS #1329
3333 MELTON RD, SANGER, TX 76266