IH 35W (CSJ: 0081-13-065)

From: Dale Earnhardt Way To: 0.7 Mile S of FM 407, Denton, TX, 76201
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025015591
$244.5M
Project Value
457,394
Square Feet
$535/sqft
Cost/SqFt
3y 1mo
Duration
Registered:Apr 1, 2025
Start:Feb 1, 2028
Target:Feb 1, 2031
Remaining:1879 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of northbound/southbound frontage roads, main lanes, exit and entrance ramps.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 1, 2025
Review Complete
April 1, 2025
Construction Start
February 1, 2028
Expected Completion
February 1, 2031

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025015591

Design Firm

๐Ÿ›๏ธ
STANTEC
5 projects ยท $316.4M
6080 Tennyson Pkwy, Suite 200, Plano, Texas 75024

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201