๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Take 5 Lake Jackson
125 Hwy 332 W, Lake Jackson, TX, 77566
Construction50%
๐Project Metrics
TDLR #TABS2025016382$850K
Project Value
1,682
Square Feet
$505/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Apr 10, 2025
Start:Apr 8, 2025
Target:Oct 8, 2026
Remaining:302 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New express Oil Change Facility
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 10, 2025
Review Complete
April 10, 2025
Construction Start
April 8, 2025
Expected Completion
October 8, 2026
Property Owner
๐ค
Take 5 Properties SPV LLC
Contact: Cristian J Aguirre Murillo
6 projects ยท $5.1M
440 S Church St, Charlotte, North Carolina 28202