📝Review Complete🔧 Alteration/Renovation💵 This project is privately funded, on private land for private use.
ENCORE BANK
301 West Ave. Suite 120, Austin, TX, 78702
📊Project Overview
$300K
Est. Cost
2,127
Square Feet
3 months
Duration
Complete
Status
📋Scope of Work
Remodel of existing office space for current tenant.
📅Project Timeline
Registered
April 14, 2025
Review Complete
April 14, 2025
Construction Start
May 5, 2025
Expected Completion
July 31, 2025
🗺️Location
📄Related Austin Permits
City permits found at this location
SLC - W 3RD ST 800-900blk-Repair Pavers
123 ft awayRepair 1.5 section of 20 driveway approach. Shall meet all city standards. **cr
ExpiredDriveway / SidewalksRepairMay 2019
Details
2019-067783 DS
300 WEST AVE BLDG A&B
164 ft awayELLE WEST APTS # 4138- GAS LINE PRESSURE TEST
FinalPlumbing PermitRepairSep 2025
Details
2025-121890 PP
🔧Airco Mechanical
300 WEST AVE
164 ft awayEXTERIOR REMODEL RE-ROOF ONLY
FinalBuilding PermitRemodelSep 2025
Details
2025-104959 BP
🔧DG Roofing, LLC
300 WEST AVE
164 ft awayTenant smelled gas plumbing company could not find leak Gas test needed to ensure no leaks in system. Laundry room.
FinalPlumbing PermitRepairMay 2025
Details
2025-059433 PP
🔧Cornerstone Plumbing and Mechanical
300 WEST AVE
164 ft awayilluminated wall sign with raceway behind the letters
FinalElectrical PermitWallNov 2024
Details
2024-148608 EP
300 WEST AVE UNIT 1322
164 ft awayCHANGE OF USE from retail to personal services with interior remodel.
FinalPlumbing PermitRemodelFeb 2022
Details
2022-009034 PP
Property Owner
Design Firm
Registered Specialist
📋
JOSHUA T,RONSON
RAS #1596
161 COREOPSIS CV, KYLE, TX 78640
(512) 892-1383