๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Mitchell Intermediate School
6800 Alden Bridge Dr, The Woodlands, TX, 77382
Construction50%
๐Project Metrics
TDLR #TABS2025016581$5.0M
Project Value
135,000
Square Feet
$37/sqft
Cost/SqFt
1y 3mo
Duration
Registered:Apr 14, 2025
Start:Jun 2, 2025
Target:Sep 1, 2026
Remaining:265 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
driveway adjustment, maintenance to chillers, boiler, air handlers, generator, cooler/ freezer condenser, and safety/ security upgrades
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 14, 2025
Review Complete
April 14, 2025
Construction Start
June 2, 2025
Expected Completion
September 1, 2026
Property Owner
๐ค
Conroe ISD
Contact: Easy Foster
6 projects ยท $51.0M
3205 West Davis St., Conroe, Texas 77304