๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Wester Middle School Addition and Reno
1520 Walnut Creek Drive, Mansfield, TX, 76063
Construction50%
๐Project Metrics
TDLR #TABS2025016754$50K
Project Value
100,736
Square Feet
$0/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Apr 16, 2025
Start:Jun 1, 2026
Target:Jul 1, 2027
Remaining:559 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Addition and Renovation
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 16, 2025
Review Complete
April 16, 2025
Construction Start
June 1, 2026
Expected Completion
July 1, 2027
๐Related Projects
๐คSame Owner
$18.7M total๐๏ธSame Design Firm
$18.4M total๐Nearby Projects
Within 1 kmProperty Owner
๐ค
Mansfield ISD
Contact: Garry Walker
4 projects ยท $18.7M
605 E Broad St #500, Mansfield, Texas 76063