๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Wildspring Phase 2
NW corner of CR 175 and CR 177, Leander, TX, 78641
๐Project Overview
$456K
Est. Cost
1
Square Feet
1 year
Duration
274
Days Left
๐Scope of Work
Construction of pedestrian ramp, 5' Sidewalk, 6' Sidewalk, 6' Concrete Trail, and 10' Concrete Trail for one (1) section of single-family residential subdivision.
๐ Project Timeline
Registered
April 17, 2025
Review Complete
April 17, 2025
Construction Start
September 1, 2025
Expected Completion
September 1, 2026
๐บ๏ธLocation
๐Related Projects
๐คMore by Toll Southwest LLC
Property Owner
๐ค
Toll Southwest LLC
Contact: Kyle Ninness
3 total projects
1320 Arrow Point Dr., Suite 401, Cedar Park, Texas 78613
303-263-7132
Design Firm
Registered Specialist
๐
JESUS E,LARDIZABAL
RAS #1051
3616 FAR WEST BLVD # 117288, AUSTIN, TX 78731
(512) 410-7059