๐Review Complete๐ง Alteration/Renovation๐ต This project is privately funded, on private land for private use.
Shimadzu Warehouse Finish-out
9701 Dessau Rd Bldg 7, Austin, TX, 78754
๐Project Overview
$990K
Est. Cost
10,987
Square Feet
1y 6mo
Duration
366
Days Left
๐Scope of Work
High pile storage rack install. Clean room kit install.
๐ Project Timeline
Registered
April 23, 2025
Review Complete
April 23, 2025
Construction Start
June 1, 2025
Expected Completion
December 1, 2026
๐บ๏ธLocation
๐Related Projects
๐Related Austin Permits
City permits found at this location
9615 MARSTON LN
154 ft awayreplace exterior door to existing sfr
ExpiredBuilding PermitRepairJan 2018
๐งSuttin Construction
9615 Marston Ln
154 ft awayChangeout Hvac To Exsting Resid Only
FinalMechanical PermitRemodelJun 2006
๐งAlonso's A/c and appliances
9615 Marston Lane A 00000
154 ft awayPulled Gas Meter Residence
FinalPlumbing PermitRemodelMar 1996
Property Owner
๐ค
SL PROJECT TEXAS 2 LP
Contact: Philip Southwick
100 CRESCENT CT STE 850, DALLAS, Texas 75201
512.236.0004
Design Firm
๐๏ธ
Holder +Southwick Architects
6 total projects
4202 Spicewood Sps Rd 214, Austin, Texas 78759
(512) 345-8817
Registered Specialist
๐
ROBIN,ROBERTS
RAS #12
401 FRANKLIN ST, HOUSTON, TX 77002
(512) 291-5994
Tenant
๐ข
Tara Stromberg
512-809-2792