๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MISD Bond - Pkg 3 - Elem Group A - Lamar Sprinklers

3200 Kessler Ave, Midland, TX, 79701
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025017420
$2.8M
Project Value
62,641
Square Feet
$45/sqft
Cost/SqFt
4 months
Duration
Registered:Apr 24, 2025
Start:May 24, 2025
Target:Sep 30, 2025
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Installation of sprinkler paping, utility work for connection & ceiling replacement 62,641sf

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 24, 2025
Review Complete
April 24, 2025
Construction Start
May 24, 2025
Expected Completion
September 30, 2025

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025017420

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
LANDY,PERKINS
RAS #371
231 SUGARTREE CIR, LIPAN, TX 76462