๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Northpoint
10860 Crystal Falls Pkwy, Building 10, Leander, TX, 78641
๐Project Overview
$4.2M
Est. Cost
38,521
Square Feet
7 months
Duration
31
Days Left
๐Scope of Work
Interior Finish-out for a religious place of Worship
๐ Project Timeline
Registered
April 25, 2025
Review Complete
April 25, 2025
Construction Start
June 1, 2025
Expected Completion
December 31, 2025
๐บ๏ธLocation
๐Related Projects
๐คMore by Northpoint Austin
Property Owner
๐ค
Northpoint Austin
Contact: Justin Giebelhaus
2 total projects
1320 Arrow Point Dr. Suite 201, Cedar Park, Texas 78613
(512) 589-2325
Design Firm
๐๏ธ
Studio Indigo
6 total projects
14205 N. Mopac Expressway, Suite 100B, Austin, Texas 78728
(865) 228-7440
Registered Specialist
๐
STEVE R,ZOERNER
RAS #1163
STE C400 NO 545 166 HARGRAVES DR, AUSTIN, TX 78737
(512) 731-9270