๐Review Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Project Layla
SEC S. County Rd 1235 & Cholla Rd, Midland, TX, 79706
Construction50%
๐Project Metrics
TDLR #TABS2025017876$14.8M
Project Value
126,670
Square Feet
$117/sqft
Cost/SqFt
10 months
Duration
Registered:Apr 30, 2025
Start:Sep 17, 2025
Target:Jul 14, 2026
Remaining:216 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New commercial construction of a warehouse building of approximately 126,670 SF. Project includes an exterior steel canopy, approximately 29,112 SF, and exterior employee parking and site work.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 30, 2025
Review Complete
April 30, 2025
Construction Start
September 17, 2025
Expected Completion
July 14, 2026
๐Related Projects
Property Owner
๐ค
Kenneth Huseman Family Partnership, L.P.
Contact: Jonathan Huseman
c/o Reeb Law PLLC, 2501 Earl Lane Suite 709, Fort Worth, Texas 76107
Design Firm
๐๏ธ
SGA Design Group, P.C.
6 projects ยท $5.2M
1437 S Boulder Ave Suite 550, Tulsa, Oklahoma 74119