โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

District 7 Neighborhood Sidewalk Improvements - Cincinnati Ave

Cincinnati Ave - Wilson Blvd to S Josephine Dr, San Antonio, TX, 78201
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025018007
$262K
Project Value
20,322
Square Feet
$13/sqft
Cost/SqFt
1 months
Duration
Registered:May 1, 2025
Start:Apr 13, 2025
Target:May 8, 2025
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Construction of approximately 20,322 sf of sidewalks, driveways, curb ramps, and other pedestrian related facilities.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 1, 2025
Inspection Complete
May 1, 2025
Construction Start
April 13, 2025
Expected Completion
May 8, 2025

๐Ÿ—บ๏ธProject Location

Loading map...

Quick Actions

TDLR ID: TABS2025018007

Design Firm

๐Ÿ›๏ธ
CobbFendley
2 projects ยท $13.5M
401 Isom Road suite 101, San Antonio, Texas 78216

Registered Accessibility Specialist

๐Ÿ“‹
SARAH W,VASQUEZ
RAS #1160
18911 HARDY OAK BLVD STE 117, SAN ANTONIO, TX 78258